Beaverton staff developed a one-page handout in collaboration with Tigard staff to show what’s happening in River Terrace and South Cooper Mountain. View the handout. In addition to showing the status of several private development projects at a glance, it also shows the public improvements that are underway or planned in the near future. These types of improvements are known as Capital Improvement (CIP) Projects, and include things like Washington County’s Roy Rogers Road widening project.

BUILDING PERMITS

  • Polygon Northwest has submitted 167 building permits for individual homes. The city has reviewed and issued roughly one-quarter of them.

ROAD IMPROVEMENTS

  • Roy Rogers Road – This road widening project is currently in the preliminary design phase. Construction is scheduled to begin in 2018 and be completed by the end of 2019. Check out the county’s Roy Rogers Road Project webpage for more details.
  • 150th Avenue – Polygon Northwest will completely re-build this road between Woodhue Street and Cabernet Drive and make additional improvements at the 150th Ave/Bull Mountain Rd intersection. For more details, contact Mike White at 503-718-2464.